Sep2025

September 17, 2025 through September XX, 2025

  • Stucco maintenance by J & C Stucco And Stone (Jason and Camille)
  • Steve, the project lead, came by with Jason on Sunday (14th) to review the project, we did a walk around
  • Crew delivered a trailer and scaffolding Monday evening (15th)

September 17, 2025, Wednesday

  • Steve, Jake, XXXX, XXXX began work starting with the shop
    • removed a portion of each garage door upright, leaving enough for a full-length gap seal to be installed
    • replaced 2-by framing member on right-hand side of A-door, it had rotted through.
    • foamed all holes
    • cleaned all bands and window sills
    • skim coated all

September 18, 2025, Thursday

  • Continued work on shop
  • working counter-clockwise around the house, started on west side of garage
  • cleaned sills and bands wherever there was damage
  • cleaned up the area behind gas regulator
  • cleaned up the vertical surfaces of the front steps and porch
    • after discussion with Steve, decided to follow his suggestion and renew the steps with stucco again, instead of our first thought of cleaning off the stucco and finishing the concrete
  • after opening a couple of sample areas on the bubbled wall, the substrate layer looks good. The color layers had delaminated, probably from water penetration
    • further stucco removal will reveal if there are more serious troubles